# Instance: Project Management & Engineering for Kingsford Hotel Bacolod (A/B run)

**WBS leaves served:** 1.1, 1.2, 1.3, 1.4, 1.5
**Module ref:** `_playbook/modules/bms/project-management-engineering.md`
**Project:** Kingsford Hotel Bacolod — BMS Rehabilitation (A/B run)

## Project-specific parameter values

- Project duration: 14 weeks (A-006)
- Engineering deliverables: shop drawings (panel GA, cable schedule, network arch, riser); programming docs; FAT plan; SAT plan; O&M manual outline; as-built drawing pack
- FAT scope: head-end + 1× sample MCP (MCP-PLANT) at our integration shop, 1 day, customer-witnessed
- Site survey (W1 of installation): existing conditions, panel locations, cable routes, existing-BMS inventory if any (per Q-001)

## BOQ line items (Phase 6 input)

| Item | Unit | Qty | Notes |
|------|------|-----|-------|
| Project Manager (full duration) | mo | 4 | 1 PM W1–W14 |
| Engineering Lead (full duration) | mo | 4 | 1 EL W1–W14 |
| Site Supervisor | mo | 4 | 1 SS W3–W14 |
| Engineering deliverables (shop drawings, panel GA, network arch, cable schedule, panel BOM, riser) | lot | 1 | Bundle of 8 deliverables |
| FAT (1-day customer-witnessed at integration shop) | lot | 1 | Includes head-end + 1× MCP, sample programming, sample graphics |
| Submittal review/approval cycle | lot | 1 | 3 review rounds assumed |
| Site survey + existing-system inventory | lot | 1 | W1; output feeds re-confirmation of A1, A3, A4 |

## Open assumptions

- A-005 (commercial), A-006 (schedule), A-008 (cutover phasing).

## Cross-references

- Working docs: A1, A2, A3, A4, A5, A6, A7, B1, B2, B3, B4, C1, C2, C3, D1, D2, D3
- Assumptions: A-001, A-005, A-006, A-008, A-009
- Clarifications: Q-001, Q-006, Q-009, Q-010