phase_1_station:
  description: "Phase 1: Stations to Depot Admin OCC Integration"
  rows:
    - particular: "Communication Network (Station to Depot-OCC)"
      rotem: true
      civil_contractor: false
      new_contractor: false
      notes: "REC IP-MPLS backbone — A-201"
    - particular: "L2 Network Switch (24-Ethernet port + 4-SFP port) at station"
      rotem: false
      civil_contractor: true
      new_contractor: false
      notes: "Per-station respective contractor (D-017) — labeled 'Civil Contractor' generically in TOR §12"
    - particular: "Fire Alarm Control Panel (FACP)"
      rotem: false
      civil_contractor: true
      new_contractor: false
      notes: "Per-station respective contractor; Notifier NFS2-3030 model per ANNEX_D1"
    - particular: "Access Gathering Panel (AGP)"
      rotem: false
      civil_contractor: true
      new_contractor: false
      notes: "Per-station respective contractor"
    - particular: "Additional Gateway or Interface Card at station"
      rotem: false
      civil_contractor: false
      new_contractor: true
      notes: "OUR scope: 1 FDAS gateway + 1 ACS gateway per station × 12 stations = 24 gateways"

phase_1_depot_occ:
  description: "Phase 1: Depot-OCC integration"
  rows:
    - particular: "FDAS Workstation Computer System @ OCC"
      rotem: false
      civil_contractor: false
      new_contractor: true
      notes: "OUR scope; INTEG BOQ row 1; ANNEX_C1 §1123.2.8"
    - particular: "ACS Workstation Computer System @ OCC"
      rotem: false
      civil_contractor: false
      new_contractor: true
      notes: "OUR scope; INTEG BOQ row 2; ANNEX_C1 §1124.2.6"
    - particular: "Control and Communication Cable (Workstation ↔ CER) @ OCC"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Raceway and Conduit (Workstation ↔ CER) @ OCC"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Additional Gateway or Interface Card @ OCC"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Table and Chair (p.s) @ OCC"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Other equipment and accessories to complete the system"
      rotem: false
      civil_contractor: false
      new_contractor: true

phase_2_site_dev:
  description: "Phase 2: Site Development"
  rows:
    - particular: "Site Development Underground Conduit (Interbuilding Connections)"
      rotem: true  # marked under ROTEM column in TOR §12
      civil_contractor: false
      new_contractor: false
      notes: "EXCLUDED from our scope per TOR §9.1 (D-010)"
    - particular: "FDAS and ACS Control and Communication Cables (Interbuilding Connections)"
      rotem: false
      civil_contractor: false
      new_contractor: true
      notes: "OUR scope; INTEG BOQ row 8"

phase_2_depot_admin_fccr:
  description: "Phase 2: Depot Admin FCCR (CP2)"
  rows:
    - particular: "FDAS Workstation Computer System @ FCCR"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "ACS Workstation Computer System @ FCCR"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "L2 Network Switch (24-Ethernet + 4-SFP) @ FCCR"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Raceway and Conduit (additional) @ FCCR"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Additional Gateway or Interface Card @ FCCR"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Table and Chair (p.s) @ FCCR"
      rotem: false
      civil_contractor: false
      new_contractor: true
    - particular: "Other equipment and accessories to complete the system"
      rotem: false
      civil_contractor: false
      new_contractor: true

phase_2_depot_om:
  description: "Phase 2: Depot O&M (CP3)"
  rows:
    - particular: "FACP @ Depot O&M"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "AGP @ Depot O&M"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "L2 Network Switch (24-Ethernet + 4-SFP) @ Depot O&M"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "Other equipment and accessories"
      rotem: false
      civil_contractor: false
      new_contractor: true

phase_2_aux_building:
  description: "Phase 2: Aux Building (CP3)"
  rows:
    - particular: "FACP @ Aux Building"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "AGP @ Aux Building"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "L2 Network Switch @ Aux Building"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "Other equipment and accessories"
      rotem: false
      civil_contractor: false
      new_contractor: true

phase_2_depot_tpssr:
  description: "Phase 2: Depot TPSSR (CP3)"
  rows:
    - particular: "FACP @ Depot TPSSR"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "AGP @ Depot TPSSR"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "Other equipment and accessories"
      rotem: false
      civil_contractor: false
      new_contractor: true

phase_2_genset:
  description: "Phase 2: Genset Building"
  rows:
    - particular: "FDAS Devices @ Genset"
      rotem: false
      civil_contractor: false
      new_contractor: true
      notes: "OUR scope — smoke/heat/pull stations/horn-strobes (per A1 GENSET-FDAS-001 to 005)"
    - particular: "AGP @ Genset"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "Other equipment and accessories"
      rotem: false
      civil_contractor: false
      new_contractor: true

phase_2_pump_houses_stp:
  description: "Phase 2: Pump Houses 1&2, STP"
  rows:
    - particular: "FACP @ PH1, PH2, STP"
      rotem: true
      civil_contractor: false
      new_contractor: false
    - particular: "Other equipment and accessories"
      rotem: false
      civil_contractor: false
      new_contractor: true

phase_2_guard_houses:
  description: "Phase 2: Guard Houses (GH-1, GH-2A, GH-2D)"
  rows:
    - particular: "FDAS Devices @ Guard Houses"
      rotem: false
      civil_contractor: false
      new_contractor: true
      notes: "OUR scope — smoke + manual pull + horn-strobe per Guard House (3 buildings)"
    - particular: "Other equipment and accessories"
      rotem: false
      civil_contractor: false
      new_contractor: true

summary:
  our_scope_summary: |
    Per Resp. Matrix + TOR §4 + D-017:
    1. Workstation systems (FDAS + ACS) at OCC + FCCR (4 systems total) — full supply + install
    2. Gateway / IF-card per station (12) + per depot integration point (~5) — full supply + install
    3. Inter-building FOC + STP cabling (Phase 2 depot scope) — full supply + install
    4. Workstation furniture (table + chairs) at OCC + FCCR
    5. FDAS field devices at Genset Building + Guard Houses (3 GH) — full supply + install
    6. Cable terminations + raceway + conduit at OCC + FCCR + building stub-ups
    7. Surge protectors at every inter-building termination
    8. All engineering deliverables (design, ICD, T&C plan, method statements, as-built)
    9. T&C, FAT, training, O&M manual, 2-yr spare parts, 3-yr software support
  excluded_summary: |
    1. Site-development underground conduit/ductbank/manholes (TOR §9.1 — Civil Contractor / REC)
    2. FACPs (Notifier NFS2-3030) at all stations + most depot buildings (per-station/per-building contractor)
    3. ACS controllers (Suprema CS-40) at all stations + most depot buildings (per-station/per-building contractor)
    4. Communication Network Station↔Depot OCC IP-MPLS (ROTEM)
    5. L2 switches at stations + ROTEM-supplied locations
    6. AGPs at most depot buildings (ROTEM)
    7. EMCS (out of scope per D-015)
    8. Stations 13 + 14 (out of scope per D-015 + TOR §4.1)
    9. Reader-side wiring + door hardware at stations + depot (per-station/Civil Contractor scope)