# B3 — Commissioning Point Inventory
# Per TOR §4.21 (Standalone + Integration + Performance) + ANNEX_C1 §1128

metadata:
  project: "SMC MRT-7 FDAS+ACS Integration"
  date: "2026-04-29"

standalone_test:
  description: "Each panel-node + workstation tested in isolation per TOR §4.21.1"
  fdas_panels_to_test: 17  # 12 stations + 5 depot
  acs_controllers_to_test: 17
  hours_per_fdas_panel: 4
  hours_per_acs_controller: 3
  total_standalone_hours_fdas: 68
  total_standalone_hours_acs: 51
  total_standalone_hours: 119

integration_test:
  description: "End-to-end station-FACP/CS-40 → gateway → IP-MPLS → CER → OCC/FCCR → workstation alarm display per TOR §4.21.2"
  paths_to_test_fdas: 34  # 17 panels × 2 head-ends (OCC + FCCR)
  paths_to_test_acs: 34
  hours_per_path_fdas: 6
  hours_per_path_acs: 4
  total_integration_hours_fdas: 204
  total_integration_hours_acs: 136
  total_integration_hours: 340

performance_test:
  description: "Multi-alarm + load + response-time + failover (if scoped) per TOR §4.21.3"
  scenarios_fdas: 8
  scenarios_acs: 6
  hours_per_scenario: 3
  total_performance_hours: 42

device_walk_test:
  description: "Device-level addressing + walk-test for FDAS field devices in our scope"
  devices_to_test: 24  # Genset 12 + Guard Houses 12
  minutes_per_device: 5
  total_walk_test_hours: 2

cable_pre_commissioning_test:
  description: "Pre-T&C cable tests (continuity + OTDR for FOC + Cat6A test)"
  foc_terminations_to_test: 36  # OTDR per fiber
  cat6a_drops_to_test: 60  # RJ45
  hours_total: 30  # OTDR + Cat6A test labor

documentation_and_reports:
  description: "T&C plans + scripts + reports per TOR §4.16 + §4.21"
  hours: 50

final_acceptance_test_with_dotr:
  description: "Final acceptance with SMC + DOTr signed certificate"
  hours: 16  # 2 days × 8 hr

total_tc_hours: 599
notes: |
  T&C window typically last 30-45 days of 180 CD per D-009 + project schedule.
  Not included here: FAT travel days (separate D-016 line items in BOQ).